Goose Project Update

B2Gold Corporation (“B2Gold”)
Registration No. BC0776025
Registered as an external company in Namibia
ISIN Code: CA11777Q2099
NSX Share Code: B2G

B2Gold Provides Construction Update for the Goose Project in Nunavut,
Canada; Construction on Budget and on Track to Pour First Gold in Q1 2025

Vancouver, BC, September 18, 2023 – B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) (“B2Gold” or the “Company”) is pleased to provide a
construction update on the Goose Project, located in the 100% owned Back River Gold District in Nunavut, Canada. B2Gold acquired the Back River Gold District as part
of the acquisition of Sabina Gold & Silver (“Sabina”) in April 2023.

Goose Project Update Highlights
    •   Goose Project on schedule for first gold pour in Q1 2025: All long lead items for the 2024 construction season have been received at B2Gold’s freight consolidation
        points, prepped for ship transport and currently the 2023 sealift is underway, which includes delivery of 24 million litres of diesel fuel.

    •   Construction capital expenditures remain in line with June 2023 estimate of C$800 million: The updated construction capital expenditure by B2Gold of C$800
        million, plus an additional C$90 million for accelerating underground development, remains in line with B2Gold’s last estimate as of June 2023. To date, capital
        expenditures are in line with the Company’s expectations, with approximately C$530 million total cash spent on the project to date (by B2Gold and Sabina).

    •   Accelerated underground mining plan adopted to increase average gold production in the first five years to over 300,000 ounces per year: Underground
        development at the Umwelt deposit and open pit mining at the Echo deposit is progressing. The Echo open pit is scheduled to be mined out and stockpiled prior to
        process plant commissioning in order to provide tailings storage capacity.

    •   Concrete and steel work in the mill area progressing ahead of schedule: Erection of structual steel has commenced, with building cladding to begin shortly. The
        Company expects the ball mill to be set in place in December 2023, ahead of schedule, which significantly de-risks the construction schedule for mill completion and
        first gold pour in Q1 2025.
    •   Phase 1 of the accommodation complex opened in July 2023: Phase 1 of the accommodation complex includes 310 beds at the permanent site location, which
        together with the 160 beds located at the existing exploration camp, provide the necessary accommodation to support accelerated construction, mining and
        exploration activities.
    •   Earthworks necessary to extend airstrip to be completed in September 2023:
        Planned extension of the airstrip to 5,000 feet will allow large capacity, fully loaded passenger planes to land at the Goose Project during the 2024 construction campaign.

    •   Winter ice road preparations are well underway: The Request for Proposal process has closed for the selection of the winter ice road constructor and a decision is
        expected to be made before the end of September. The contractor will be managed by B2Gold’s experienced ice road construction team. The execution strategy for the 2024
        ice road season involves an earlier start to the road construction than previous years, which contributes to de-risking the trucking season. In addition, the ice road
        construction will begin from the middle and work outwards in each direction, which should enable the ice road to be completed earlier than in prior seasons.

    •   11,000 meters of drilling over 44 drill holes has been completed to date in 2023 at Back River: The drill program at the Goose Project has focused on testing the Umwelt
        and Llama deposits down-plunge for resource confirmation and resource expansion, as well as various regional targets. The drill program is anticipated to run through
        December 2023.

The full announcement can be viewed at the following link:
https://www.b2gold.com/news/b2gold-provides-construction-update-for-the-goose-project-in-
nunavut-canada-construction-on-budget-and-on-track-to-pour-first-gold-in-q1-2025

On Behalf of B2GOLD CORP.
Clive T. Johnson
President & Chief Executive Officer

19 September 2023

Registered Office
20 Nachtigal Street
Ausspannplatz
Windhoek
Namibia

Sponsor
IJG Securities (Pty) Ltd
Member of the NSX
4th floor 1@Steps,c/o Grove and Chasie Street
Kleine Kuppe, Windhoek
P O Box 186, Windhoek, Namibia
Registration No. 95/505

Date: 19-09-2023 09:02:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.

Where to find us

Namibian Stock Exchange Contacts

Tiaan Bazuin – Chief Executive Officer
Alexandrea Ullrich – Chief Financial Officer
Johene Saal – Chief Information Officer
Namene Shejavali-Lungu – Chief Regulatory Officer
 
Namibian Stock Exchange
4 Robert Mugabe Avenue
Entrance from Dr. Theo-Ben Gurirab Street
P.O.Box 2401
Windhoek
Namibia
Tel: +264 61 227 647
Fax: +264 61 248 531
E-mail: info@nsx.com.na

Transfer Secretaries Contacts

Alexandrea Ullrich – Manager
Adelheid Scholtz – Senior Administrator
Carol-Ann Meintjies – Administrator
Annetjie Diergaardt – Administrator
 
Transfer Secretaries
4 Robert Mugabe Avenue
Entrance from Dr. Theo-Ben Gurirab Street
P.O.Box 2401
Windhoek
Namibia
Tel: +264 61 227 647
Fax: +264 61 248 531
E-mail: ts@nsx.com.na
© 2021 Namibian Stock Exchange

Trading Days

Want to trade?

Weekly Trading Reports